Biomass test plant in Dürnrohr (Austria 2008)
- Test plant for pyrolisis of straw
- Generation of electric power and district heating
- 5 MW
Biomass heating plant in Zurich / Aubrugg (Switzerland 2010)
- Fluidised-bed combustion of wood chips
- Generation of electric power and district heating
- 40 MW
Fluidised-bed reactor for ABRG Arnoldstein (Austria 2010)
- Fluidised-bed combustion of hard, fluid and pasty waste
- Electric power and supply for the local steam network
- 11MW
Biomass heating reactor Heiligenkreuz (Austria 2009)
- Fluidised-bed combustion for biomass
- Electric power and process steam
- 40 MW
Fluidised-bed installation McStep (Switzerland / Monthey 2010)
- Fluidised-bed combustion of sludge and solvent
- Process steam for a industrial plant
- 7 MW
Fluidised-bed installation Villas Energie GmbH (Austria 2008)
- Fluidised-bed combustion of enterprise-internal production waste and sludge
- Heat transfer into the thermal oil system
- 5 MW
Waste combustion plant (Malta 2009)
- Reconstruction of a combustion installation in a slaughterhouse
- Combustion of hospital waste and other garbage
- Cooling by refrigerating machine operated by heat
- 5 MW
Wood power station Basel (Switzerland 2008)
- Fluidised-bed combustion of wood chips
- Electrical power and district heating
- 30 MW
Biomass heating plant Altenstadt-Schongau (Germany 2005)
- Reconstruction of a fluidised-bed installation
- Electric power and district heat
- 40,4 MW
Waste combustion plant MSZ 3 Moskau (Russia 2007)
- Stoker-fired furnace of domestic waste
- Electric power for the own use and district heat
- 2 x 45 MW thermal
Biomass heating plant OIE Neubrücke (Germany 2003)
- Fluidised-bed combustion for biomass and waste wood
- Electric Power and district heat
- 30 MW